Cebu Cordova Link Expressway - Construction Update #8

Cebu Cordova Link Expressway - Construction Update #8 11 December 2019

After completing the mounting of the Girders at the 1st, 2nd and 3rd span, they started mounting the prefabricated bottom slabs. This will serve as a permanent formwork for the top slab.

The slab mounting work started at the 3rd span since the Construction Barge is positioned there. Mounting of the slabs at the 3rd span is almost complete, they are now working at the 2nd span.

At the Off Ramp, the Pile Driving Team continued boring, installing the rebars and concreting.

Another Team is also working at CN8 (Foundation #8) installing formworks for the Headstock.